How to handle the difficulty of Zhuhai foundation pit construction? Huma gives the answer online!
Release time:
2020-02-09
During the construction of a foundation pit in Zhuhai, serious groundwater leakage and high sediment content greatly increased the difficulty of construction and affected the efficiency of the project. But our company's cable duct blocker effectively solves this problem.
During the construction of a foundation pit in Zhuhai, serious groundwater leakage and high sediment content greatly increased the difficulty of construction and affected the efficiency of the project. But our company's cable duct blocker effectively solves this problem.

The reasons are as follows:
1. The cable pipe diameter is large, resulting in large gaps and poor sealing.
2. The large underground water flow makes construction difficult.

To solve the problem of foundation pit sealing in the offshore city of Zhuhai, our company's technical personnel provided on-site guidance for a week on the installation of cable and pipeline sealing devices. With the combination of the sealing requirements of the demander and everyone's full support, we have successfully solved the sealing problem of the Zhuhai foundation pit and received unanimous praise!

Related News