How to deal with the difficulty of Zhuhai foundation pit construction? Henma gives the answer online!

How to deal with the difficulty of Zhuhai foundation pit construction? Henma gives the answer online!

Author:
Source:
Release time:
2020/02/09

When a certain project in Zhuhai was constructed in a foundation pit, the groundwater leakage was serious and the content of sediment was large, which greatly increased the difficulty of construction and affected the efficiency of the project. But our company's cable duct plugging device solves this problem very well.

48

The reasons are as follows:

1. The large diameter of the cable leads to large gaps and poor sealing.

2. Large groundwater flow makes construction difficult.

23

In order to solve the problem of blocking the foundation pit in Zhuhai, a maritime city, our company's technicians conducted a week-long instruction on the installation of the cable pipe plugging device. In combination with the demand-side plugging requirements and everyone's full support, the Zhuhai foundation pit plugging problem has been completely solved and won unanimous praise!

88